Follow the construction and journey that will deliver
@Everton
Football Club's new waterfront home. Stay tuned for news of our unique matchday experiences!
The jaw-dropping scale of the steep-tiered south stand - which will house more than 13,000 Evertonians - is visible for the first time following the installation of terracing. 🏟
🧱 | The first of a grand total of 731 brick façade panels have been installed!
Once complete, the façade will incorporate elements of the historic Goodison Park latticework pioneered by the famous Scottish stadium architect, Archibald Leitch.
“I think fans are going to be very surprised how loud this building is going to be and feeling like all that noise is right on top of the pitch."
#EFC
's Stadium Concept Design Guardian
@MeisArch
answered YOUR questions in a special podcast - out now! 🔊
🏗️ | The last roof purlin has been slotted into place to complete the roof structure.
Internally, the first giant speaker system has also been secured into the roofing steelwork, while work continues to glaze the rear of the north stand, which now has seating across the entire…
🏟️ | Everton Stadium and the City of Liverpool has been shortlisted as part of the UK and Ireland’s preliminary bid dossier to host
@UEFA
#EURO2028
.
🗞️
Can you spot the subtle Goodison Park latticework pattern - pioneered by the famous Scottish stadium architect, Archibald Leitch - emerging in the external brickwork at Everton Stadium? 🏟👀
Workers at
@Laing_ORourke
have entered the seasonal spirit by creating a new mini-pitch to mark the centre of Everton Stadium - complete with fake grass and pitch markings!
The flag marks the spot where
@Everton
will kick off at the start of the 2025/26 season. 🏟
A glimpse into the finished façade of the stadium, following the installation of metal infill panels that provide a contrast with the brickwork across all four stands 🏟️
Last week our Stadium Design Concept Guardian
@Meisarch
visited the site to check the stunning progress of the project which, two years into the build, remains firmly on schedule and is set to be completed in the final months of 2024...
The final steelwork has been installed in the north stand at Everton Stadium.
The two separate sections have been conjoined, just 15 weeks since the first 18-tonne super column was installed in the north west quadrant to commence the steelwork phase of the development. 🏟
🚧 | As
@Everton
's new stadium continues to rise into the north Liverpool skyline, work continues to bring back to life one of the site’s key historical features...
A bird’s eye view of the amazing progress 🤩
Raker beams are now installed in the fast-developing east stand, with the west stand also a hive of activity.
Meanwhile, roof trusses can be seen being assembled in the two temporary structures pitchside.
✅ | The stadium structure has now been completed just 20 months after work began! 🏟️
Work will now focus on completing the roofing structure on the west and east stands and the fit-out on numerous levels of the two main stands.
@Laing_ORourke
🔵