Another 1000 RKM Electrification work will be ready by end of September 2019.
Government of India is committed to provide fast,efficient and safe Rail transportation through Railway Electrification.
First Goods Train run on Electric Traction from Ahmedabad to Viram gram Successfully completed.
Approx saving of ₹ 22,200/- in one trip,450 litre of diesel saved and 1600 units of electricity spent.
@RailMinIndia
@WesternRly
@drmadiwr
Railway Electrification work of katni -satna 95 RKM in the territory of WCR completed on 29.06.2020. Total electrification completed by CORE in 2020-21 stands 181 RKM. Journey from Mumbai to Howrah/Patna will now be without traction change in between.
First Electric Double stack containerTrain ran successfully fromPalanpur toBotad via MSH(Gr187) VG (Gr213)SUNR (Gr212)and reachedBotad today at around11.45Hrs after covering270RKM.This is the first loaded double stack container train onElectricTraction with High Rise pantographs.
CRS inspection of Salem-Vriddhachalam section (136 RKM) of Salem Division in Southern Railway completed successfully on 28.12.2021. With this total 1192.81 RKM route have been electrified by CORE in the current FY.
OHE energisation, earth fault test followed by AC loco trial in Birur Arsikere section of Mysuru Division of South Western Railway (42 RKM) completed successfully in UP & DN both directions on 28.11.22.
@RailMinIndia
@SWRRLY
#missionelectrification
OHE energisation, earth fault test followed by Light engine trial of Gadag bypass line of Hubli Division SWR (1.84 RKM, 3.54 TKM) completed successfully in UP & DN both directions.
@SWRRLY
Inspection of Railway Electrification works followed by speed trial at full sectional speed in Hosdurga (Excl)- Birur (Incl) Section (38.7 RKM /91.72 TKM Double line), MYS Division of South Western Railway completed successfully today.
@SWRRLY
CRS inspection of Barabanki-Ayodhya Cantt. (99.25 RKM) Lucknow Division in Northen Railway completed successfully on 30.03.2022. With this total 4220.26 RKM route have been electrified by CORE in the current FY.
@RailMinIndia
@GM_NRly
CRS inspection of Gadwal-Raichur section (57.7 RKM) of Hyderabd Decan Nampally & Guntakal Division in South Cetral Railway completed successfully on 21.12.2021. With this total 1032.81 RKM route have been electrified by CORE in the current FY.
CRS inspection of Dhalgaon - Kurduwadi section (125 RKM) of Solapur Division in Central Railway completed successfully on 04.03.2021. With this total 1337 RKM route have been electrified by CORE in the current FY.
CRS inspection of Jogighopa-Boka section (86 RKM) of Rangiya Division in Northeast Frontier Railway completed. With this total 2780.24 RKM route have been electrified by CORE in the current FY.
@RailMinIndia
@gm_nfr
CRS inspection of Morthad-Nizamabad section (45.10 RKM) in South Central Railway completed successfully on 24.02.2022. With this, total 2149.54 RKM route have been electrified by CORE in the current FY.
@RailMinIndia
@gmscrailway
@drmsecunderabad
Statutory inspection of RE works followed by speed trial at full sectional speed(110 Kmph) in Ausa Road–Latur Road(50 RKM/58.36TKM)single line section of Solapur Div. of CR completed successfully. With this total commissioning by CORE during (2022-23) is 2808.3RKM/3842.3TKM
CRS inspection of Guwahati-Digaru-Jagi Road section (56.78 RKM) of Lamding Division in North Forntier Railway completed successfully on 28.02.2022. With this, total route electrified by CORE in the current FY stands 2309 RKM.
@RailMinIndia
@gm_nfr
@drmnfr_lmg
Statutory inspection of Railway Electrification works followed by speed trial at full sectional speed (100 Kmph) in Barmer-Gadra Road (80.708 RKM/89.334 TKM) single line section of Jodhpur Division of NWR successfully completed.
RE team ready for final fitment of OHE prior to introduction of Electric traction system in Palanpur Mahesana Ahmedabad Section, by the end of Aug'19.Thunderbolt rain is going on in Mahesana unjha Palanpur section.
@RailMinIndia
@WesternRly
Statutory inspection of RE works followed by speed trial at full sectional speed (70 Kmph) in Tirunelveli-Tenkasi(72.02 RKM/81.51TKM) single line section of Madurai Div. of SR completed successfully. With this total commissioning by CORE during (2022-23) is 3098.51RKM/4283.55TKM
An Electric Locomotive ,Diesel Locomotive and Steam locomotive standing together.
Puffing steam engine has become history and replaced due to technological changes.With complete electrification these humming diesel beasts will join league of steam.
CRS inspection of Railway Electrification work of Viramgam – Surendranagar 68 RKM in the territory of WR completed on 09.03.2020. With this, total electrification completed by CORE in 2019-2020 stands 2235 RKM.
CRS inspection of Hapa-Bhatiya section (109 RKM) of Rajkot Division in Western Railway completed successfully on 19.03.2021. With this total 2134 RKM route have been electrified by CORE in the current FY.
Inspection of RE works in Himayatnagar-Mudkhed (55.70 RKM /65.35 TKM) & Pokharni Narsimha - Parbhani (15.83 RKM/15.90TKM),Total : 71.53RKM/81.25TKM single line sections of Nanded Div. of SCR completed successfully. With this CORE achieves 3370.69RKM/4716.88TKM in FY 22-23
Statutory inspection of RE works followed by speed trial at full sectional speed (60 Kmph) in Kapadvanj-Modasa (59.67 RKM/60.54TKM) single line section of Vadodara Div. of WR completed successfully. With this total commissioning by CORE during (2022-23) is 3026.49RKM/4202.04TKM
CRS inspection of Railway Electrification work of Bhagalpur -Shivnarayanpur 39 RKM in the territory of ER completed on 30.06.2020. With this, total electrification completed by CORE in 2020-2021 stands 220 RKM.
CRS inspection of Yashwantpur-Tumkuru section (56 RKM) of Yashwantpur & Bangaluru Division in South Western Railway completed successfully on 29.10.2021. With this total 591 RKM route have been electrified by CORE in the current FY.
Work of Railway Electrification in full swing in Virgramgram Vaninagar section of Rajkot Division of Western Railway.
This is part of Viramgram Surendranagar section.
@RailMinIndia
@WesternRly
@wrdrmrjt
For fast execution of Electrification projects SWR and Karnatka,a project unit have been established at Banglore under Chief Project Director.The unit will also execute one section of CR and 2 sections of SCR.
@RailMinIndia
@SWRRLY
Statutory inspection of RE works followed by speed trial at full sectional speed(110 Kmph) in Sampige Road - Arsikere(62 RKM/147TKM) double line section of Mysuru Division of SWR completed successfully. With this, total commissioning by CORE during 2022-23 is 1589.7RKM/2231.5TKM
CRS inspection of Tiruchchiraplli-Karaikudi section (90 RKM) of Tiruchchiraplli & Karaikudi Division in Southern Railway completed successfully on 17.02.2022.
First electric loco hauled goods train from Katihar to New Jalpaiguri started from Katihar at 23.00 hrs on 24.12.19, passed Gunjaria at 04.01 hrs and arrived NJP at 8.08 hrs on 25.12.19 without any trouble.
@RailMinIndia
@drm_kir
@RailNf
Nittur SPGR Section of SBC Divn SWR (12 RKM, 26 TKM, Double line section): OHE energisation, earth fault test and AC loco trial completed successfully on 29.11.22.
PCEE SWR inspection for commissioning planned on 30.11.22.
@RailMinIndia
@SWRRLY
Statutory inspection of RE works followed by speed trial at full sectional speed(100 Kmph) in Tolahunse–Devaegudda(53 RKM/133TKM)double line section of Mysuru Div. of SWR completed successfully. With this total commissioning by CORE during (2022-23) is 2861.3RKM/3975.3TKM
#mission100percentelectrification
Statutory Inspection of RE works followed by speed trial at full sectional speed (110 Kmph) in Bileshwar-Rajkot Double Line section & Than-Daladi UP line section (Total-13.72RKM/49.22TKM) of Rajkot Division of WR completed.
CRS inspection of LingampeJagtiyal-Morthad section (50 RKM) of Secunderabad Division in South Central Railway completed successfully on 12.03.2021. With this total 1556 RKM route have been electrified by CORE in the current FY.
CRS inspection of Railway Electrification work of Naupada – Gunpur 90 RKM in the territory of ECoR completed on 15.03.2020. With this, total electrification completed by CORE in 2019-2020 stands 2325 RKM.
Inspection of RE works followed by speed trial at full sectional speed (110 Kmph) in Gadwal-Kurnool (53.95RKM/58.80TKM) single line section of Hyderabad Div. of SCR completed successfully. With this,CORE achieves 3576.87RKM/5030.88TKM in (2022-23). Inching towards 4000RKM
CRS inspection of Thanjavur-Thiruvarur (54 RKM) in Southern Railway successfully completed today. Total railway electrification completed by Central Organization for Railway Electrification during current FY is 1782 RKm.
Statutory Inspection of RE works followed by speed trial at full sectional speed (110 Kmph) in Jagraon- Moga-Firozpur (83RKM/103TKM) single line section of FZR Div. of NR completed. With this, CORE achieves 3993.391RKM/5588.01TKM in (22-23).
#mission100percentelectrification
Statutory Inspection of RE works followed by speed trial at full sectional speed(110 Kmph) in Dinagaon-Jalna single line section 7.2RKM/11.7TKM of Nanded Division of SCR completed.
Railway Electrification work started in the sections connecting stations of Phaphamau,Pratapgarh,Chilbila Sultanpur,Faizabad,Zafrabad, Janghai etc of Lucknow Div of Northern Railway.आज हुई भूमि-पूजन के कुछ छायाचित्र.
@RailMinIndia
@PiyushGoyalOffc
@PiyushGoyal
@GM_NRly
@drmlko25
Mast Erection under process in Amhedambad Mehsana Palanpur section as part of RE work to introduce Electric Traction in the section.
@RailMinIndia
@WesternRly
@drmadiwr
Biggest EPC tender for Electrification has been finalised by CORE covering 7 sections of South Central Railway for total 1227 RKM.
This will lead to faster completion of RE Projects.
#Mission100percentelectrification
Statutory Inspection of RE works in Solur- Kunigal (27RKM/31TKM) single line section of Bengaluru Div. of SWR completed. With this,CORE achieves 4552.527RKM/6312.269TKM in(22-23)
Congratulations Team Bengaluru!!
Statutory inspection of RE works followed by speed trial at full sectional speed (100 Kmph)in Rajula–Mahuva (31 RKM/33.39TKM) single line section of Bhavnagar Division of WR completed successfully. With this total commissioning by CORE during (2022-23) is 2577.5RKM/3528.1TKM
CRS inspection of Railway Electrification work of Lanjigarh –Junagarh 52.4 RKM in the territory of ECoR completed on 16.03.2020. With this, total electrification completed by CORE in 2019-2020 stands 2378.8 RKM.
CRS inspection of Railway Electrification work of Bandikui (excl)–Bassi(JP) 56 RKM in the territory of NWR completed on 19.03.2020. With this, total electrification completed by CORE in 2019-2020 stands 2434.8 RKM.
Statutory inspection of RE works followed by speed trial at full sectional speed (100 Kmph) in Amarsar–Bileshwar (26.52 RKM/63.04TKM)double line section of Rajkot Div. of WR completed successfully. With this total commissioning by CORE during (2022-23) is 2887.82RKM/4038.34TKM
माननीय रेल मंत्री भारत सरकार, श्री पीयूष गोयल ने आज दिनांक 29-11-2020 को केंद्रीय रेल विद्युतीकरण संगठन, प्रयागराज की जयपुर परियोजना के बांदिकुई-दिगावडा सेक्शन के विद्युत ट्रेक्शन पर मालगाड़ी को हरी झंडी दिखाकर उदघाटन किया।
Statutory inspection of RE works followed by speed trial at full sectional speed (110 Kmph) in Nittur - Sampige Road (12 RKM/27 TKM) double line section of Bengaluru Division of SW Railway completed successfully by Shri Jaipal Singh, PCEE SWR today on 30.11.2022.
@RailMinIndia
CRS inspection of Akola-Lohagad section (35 RKM) of Nanded Division in South Central Railway completed successfully on 24.03.2021. With this total 2225 RKM route have been electrified by CORE in the current FY.
Inspection of RE works followed by speed trial at full sectional speed(100Kmph) in Chikkaballapur-Chintamani (35RKM/38TKM) single line sections of Bengaluru Div. of SWR completed successfully. With this, CORE achieves 3299.16RKM/4627.57TKM in FY 22-23. Congratulations Team SBC..
Electrification completed in these challenging times and Electric Loco trial run in the Satna-Katni section of Jabalpur Division of West Central Railway completed successfully on 11.05.2020.
@gmwcrailway
@drmjabalpur
@PiyushGoyalOffc
@PiyushGoyal
Inspection of RE works followed by speed trial at full sectional speed(110Kmph) in Kamareddi-Nizamabad(49.93RKM/57.32TKM) & Jankampet-Basar(22.91RKM/26.11TKM) single line sections of HYB Div. of SCR completed successfully.With this,CORE achieves 3264.16RKM/4589.57TKM in FY 22-23
#mission100percentelectrification
Statutory inspection of Railway Electrification works followed by speed trial at full sectional speed (100 Kmph) in Samdari- Jalore (56.68 RKM/67.22 TKM) single line section of Jodhpur Division of NWR successfully completed.
RE work for electrifying large part of Southern Railway's rail network started today under EPC mode with the inuguration of RE work in Madurai-Manamadurai section in presence of GM CORE Sri Y. P. Singh..भूमि पूजन के विहंगम दृश्य
@RailMinIndia
@GMSRailway
@GMSWR
@PiyushGoyalOffc
Statutory inspection of RE works followed by speed trial at full sectional speed (100 Kmph) in Surbari-Samakhiyali(23.81RKM/57.805TKM)double line section of Ahmedabad Div. of WR completed successfully. With this, total commissioning by CORE in (2022-23) is 3191.32 RKM/4506.14TKM
#Mission100PercentElectrification
With statutory inspection of RE works in Devargudda-Karjagi-Hubballi section in MYS & UBL Div. of SWR, Jetalsar-Lushala section in BVP Div. of WR & Aurangabad-Dinagaon section in NED div. of SCR
CORE scales a new high.....
Railway Electrification is making significant progress even during Corona pandemic. CRS inspection of RE work of Sitamarhi-Muzaffarpur section of 66.6RKM in the territory of ECR completed on 05.08.2020.With this, total electrification completed by CORE in 2020-21stands 326.6 RKM
Today Electric Loco trial run completed in Miraj - Dhalgaon section of SUR divn ,CRly.
62 RKM with A.C.Loco WAP7
Miraj Dep-11:10 hrs, Dhalgaon Arrv: 12:04 hrs
@110
kmph except caution order.Seen in picture Sri K Nagendra Prasad CPD Secunderabad.
@RailMinIndia
@Central_Railway
Statutory inspection of RE works followed by speed trial at full sectional speed(90 Kmph) in Birur-Masarahalli (40RKM/45TKM) single line section of Mysuru Division of SWR completed successfully. With this, total commissioning by CORE during 2022-23 is 1629.7RKM/2276.5TKM
Statutory inspection of RE works followed by speed trial at full sectional speed(110 Kmph)in Samakhiyali–Bhachau(19.21 RKM/48.94TKM)double line section of Ahmedabad Div. of WR completed successfully. With this total commissioning by CORE during (2022-23) is 2596.7RKM/3577.04TKM
First Goods train R/JNPT completed its maiden journey on newly electrified Laxmibai nagar- Fatehbad-Ratlam section successfully with loco no 31386 WAG9. 120 km journey completed in just 2 hrs. on this single line section.
@WesternRly
@RailMinIndia
@MangalSundar
Tower wagon panto run successfully completed in Rajkot Hapa Section of Rajkot Division as preparedness for CRS inspection to be held on 09.09.19.
@RailMinIndia
@WesternRly
@wrdrmrjt
दिनांक 14.09.2020 को रेल विद्युतीकरण के इतिहास में पहली बार एक दिन में कुल 138 shot(~90TKM) वायरिंग की गई।इसके पहले दिनांक 22.02.20 को 68 shot वायरिंग एक दिन में हुयी थी।इसमें लखनऊ परियोजना का सर्वाधिक योगदान(107shot/70 TKM)रहा।
@PiyushGoyal
@RailMinIndia
@drm_moradabad
@GM_NRly
CRS inspection of Bewari-Gurya section (40 RKM) of Bikaner and Ajmer Division in North Western Railway completed successfully on 08.10.2021. With this total 508 RKM route have been electrified by CORE in the current FY.
Statutory inspection of RE works followed by speed trial at full sectional speed (100Kmph)in Parli Vaijnath–Pokharni(46.3RKM/49.5TKM)single line section of Nanded Division of SCR completed successfully.With this total commissioning by CORE during (2022-23) is 2546.5RKM/3494.68TKM
Elctrification work in Surendranagar Botad section of Bhavnagar division of WR is going on during night.Even rain could not stop the work.
The zeal and dedication of RE team is commendable.
@RailMinIndia
@WesternRly
@DRM_BVP
Inspection of RE works followed by speed trial at full sectional speed (50 Kmph) & (75 Kmph) in Verka-Dera Baba Nanak(45RKM/50TKM) and Chheharta-Atari(18RKM/27TKM)single line sections of FZR Div. of NR completed. With this,CORE achieves 3780.391RKM/5306.006TKM in (22-23).
CRS inspection of Khurdwadi-Pangri section (55.5 RKM) of Solapur Division in Cetral Railway completed successfully on 08.12.2021. With this total 975 RKM route have been electrified by CORE in the current FY.
Overhead line adjustments and other activities are under progress during heavy rains to make the targeted section Jaora Mandsor Nimach for for Electric traction by RE Ahmedabad unit.
@WesternRly
@RailMinIndia
@MangalSundar
Complete electrification of all BG routes by 2021-22 will witness running of Trains with Electric locomotives on all BG routes.This will save fuel bill of country and reduce maintainance cost of locomotives as all the diesel locomotives will be replaced with Electric Locomotives.
CRS inspection of railway electrification work of Mahenragarh-Sadulpur, 88 RKM in the territory of NWR completed on 05.03.2020. With this, total electrification completed by CORE for 2019-2020 stands 2107 RKM.
CRS insp of Miraj-Dhalgaon(62 RKM) successfully completed today. Total railway electrification completed by Central Organization for Railway Electrification during current FY (2019-20) is 1525 RKm which is 2.35% higher than the same during the corresponding period of last FY.
Statutory inspection of RE works followed by speed trial at full sectional speed (110 Kmph) in Wansjaliya-Porbandar(32.075 RKM/50.271TKM)single line section of Bhavnagar Div. of WR completed successfully.With this total commissioning by CORE in (2022-23) is 3130.59RKM/4335.46TKM